Monday, December 4, 2006

New edition of "From Dream to Reality"

The second issue of the newsletter "From Dream to reality", is now available. The Newsletter was started with the aim of updating the friends on the progress of the construction of the new National Center in Yaounde. Here are some highlights....

A computer generated model of the completed building



Some friends from the Yaounde-Soa cluster gathered at the construction site on 17th Spetember following a reflection meeting



FINANCIAL UPDATE


Total estimated cost of the project (building + land) = 110,596,415 CFA.


Income:
• Total received from the World Centre: = 66,531,896 CFA.
• Total received from individuals from abroad, individuals
from Cameroon, LSA’s, and communities in Cameroon: = 2,130,273 CFA.
TOTAL INCOME: = 68,662,169 CFA.


Expenses:
• Purchase of land, tax, notary, title deed, etc. = 13,821,678 CFA.
• Bank Charges = 11,480 CFA.
• Total expense on project as of November: (materials, labour, utilities, installation, building permit, etc.) = 9,542,505 CFA.
TOTAL EXPENSE: = 23,375,663 CFA.


BALANCE IN BANK: = 45,286,506 CFA.

ADDITIONAL AMOUNT NEEDED TO COMPLETE THE PROJECT: = 41,934,246 CFA

All this and much more in the second edition of "From Dream to reality" email a request to zionside@gmail.com for the complete issue.